LP#1635737 Due date honors variable durations
authorBill Erickson <berickxx@gmail.com>
Thu, 23 Mar 2017 18:18:34 +0000 (14:18 -0400)
committerBill Erickson <berickxx@gmail.com>
Fri, 19 May 2017 15:09:45 +0000 (11:09 -0400)
commitce6781d3cf8be919b62347ba8bf0c260cd9e07d7
tree69f310e8fd992e2b6f62d0cbeac9150074094ef9
parent7609099190455ce8662c8950e426c00552390a98
LP#1635737 Due date honors variable durations

The due date calculation now takes the length of duration components
into consideration.  For example, "1 day" may be shorter or longer than
24 hours during a time change event, "1 month" may be shorter or longer
depending on which month it is currently, etc.

Signed-off-by: Bill Erickson <berickxx@gmail.com>